Background |
| |
|
|
|
| June 2 |
2006 |
#aa |
Auditorium: Above & Below |
| June 2 |
|
#bb |
SE Basement Studio in March & May |
| June 11 |
|
#cc |
Steam Pipe Plays On |
| June 14 |
|
#dd |
Recent Auditorium Photos |
| June 14 |
|
#ee |
Steam Pipe or Time Bomb? |
| June 22 |
|
#ff |
More Interior Demolition |
| |
|
|
|
| June 29 |
2006 |
#1 |
Second Floor, Architecture Hall |
| July 1 |
|
#2 |
HVAC circa 1909 |
| July 7 |
|
#3 |
Debris Flows to First Floor |
| July 8 |
|
#4 |
Top Floor - Gutted |
| July 13 |
|
#5 |
Steam Pipe Update |
| July 14 |
|
#6 |
Frieze Rm 135 - Toast |
| July 15 |
|
#7 |
North Wing at Solar Noon |
| July 18 |
|
#8 |
Long Time, No Auditorium |
| July 18 |
|
#9 |
Coffee, Tea or Plank? |
| July 23 |
|
#10 |
Room 202 - Before & Now |
| July 26 |
|
#11 |
Lobby Stairs - Before & Now |
| July 27 |
|
#12 |
First Floor Demolition |
| July 28 |
|
#13 |
Bare Naked Stairs |
| July 29 |
|
#13a |
Elaine Remembers 202 Before 202 |
| July 30 |
|
#14 |
Auditorium, No East Wall |
| |
|
|
|
| Aug. 3 |
2006 |
#15 |
South Wing Diptych |
| Aug. 7 |
|
#16 |
Get Ready for Shear Walls |
| Aug. 7 |
|
#16a |
Here Comes the Rebar |
| Aug. 14 |
|
#17 |
Auditorium Scaffolding |
| Aug. 19 |
|
#18 |
Breather Walls Revisited |
| Aug. 19 |
|
#19 |
Breather Wall Archeology |
| Aug. 19 |
|
#20 |
Steel Stripped of Concrete |
| Aug. 21 |
|
#21 |
Steel Column Follow Up |
| Aug. 21 |
|
#22 |
Auditorium Heaven |
| Aug. 23 |
|
#23 |
Sleeper Boards, Not Joists |
| Aug. 27 |
|
#24 |
Once We Were Orange |
| Aug. 27 |
|
#24a |
No, We Were Red |
| |
|
|
|
| Sept. 10 |
2006 |
#25 |
Vertical Panorama of East Wall |
| Sept. 11 |
|
#26 |
Sleeper Board Factory |
| Sept. 14 |
|
#27 |
The Factory Condition |
| Sept. 17 |
|
#28 |
More Sleeper Archeology |
| Sept. 19 |
|
#29 |
Earthquake? Bring It On! |
| Sept. 21 |
|
#30 |
Up at the Ceiling |
| Sept. 22 |
|
#31 |
Red or Orange in 1908? |
Sept. 25
|
|
#32 |
Right on Schedule |
| Sept. 25 |
|
#33 |
Return of the Breather Walls |
| Sept. 26 |
|
#34 |
Added Scale |
| |
|
|
|
| Oct. 7 |
2006 |
#35 |
Poor Floor |
| Oct. 9 |
|
#36 |
More Floor |
| Oct. 17 |
|
#37 |
Blue Fades to Gray |
| Oct. 24 |
|
#39 |
Interior Space Transformed |
| Oct. 24 |
|
#40 |
Rooms Forming |
| Oct. 24 |
|
#41 |
Yellow Plans |
| |
|
|
|
| Nov. 3 |
2006 |
#42 |
Strangers Visit Seattle |
| Nov. 14 |
|
#43 |
Topping Off |
| Nov. 14 |
|
#44 |
Building in Diapers |
| Nov. 27 |
|
#45 |
Ceiling Salamander |
| Nov. 30 |
|
#46 |
Walk Thru Walls, Part I |
| Nov. 30 |
|
#47 |
Walk Thru Walls, Part II |
| |
|
|
|
| Dec. 3 |
2006 |
#48 |
Basement Stairs Installed |
| Dec. 4 |
|
#49 |
Steam Pipe Revisited |
| Dec. 7 |
|
#50 |
Ironworker in Exhibit Space |
| Dec. 9 |
|
#51 |
Ironworker Steels the Show |
| Dec. 18 |
|
#52 |
Behold, A Skylight! |
| Dec. 19 |
|
#53 |
Wall Framing in North Wing |
| Dec. 19 |
|
#54 |
Pajama Party in South Wing |
| Dec. 21 |
|
#55 |
North Wing in Winter |
| Dec. 27 |
|
#56 |
Pajama Party Downstairs |
| Dec. 29 |
|
#57 |
Flashback: A Tie-Back Story |
| |
|
|
|
| Jan. 1 |
2007 |
#58 |
South Wing in 2006 - 2007 |
| Jan. 3 |
|
#59 |
Ground to a Halt |
| Jan. 6 |
|
#60 |
Structure Exhibited |
| Jan. 11 |
|
#61 |
Skinny Legs Beefed Up |
| Jan. 11 |
|
#62 |
The Condon Hall Effect |
| Jan. 15 |
|
#63 |
Steam Pipe Hotspots |
| Jan. 15 |
|
#64 |
Steam Pipe Exits Building |
| Jan. 21 |
|
#65 |
New Breather Wall Chimneys |
| Jan. 22 |
|
#66 |
Auditorium Update |
| Jan. 24 |
|
#67 |
Blue Gets Plastered |
| |
|
|
|
| Feb. 1 |
2007 |
#68 |
New Coffee Shop |
| Feb. 6 |
|
#69 |
South Wing Takes Off |
| Feb. 7 |
|
#70 |
One Sink Fits All |
| Feb. 9 |
|
#71 |
Damn It, Stamets, Get It Right! |
| Feb. 22 |
|
#72 |
Stairwell Under Cover |
| Feb. 25 |
|
#73 |
North Wing Progress |
| Feb. 25 |
|
#74 |
NW Studios - Interior Walls |
| Feb. 26 |
|
#75 |
Four Exposed Steel Columns |
| Feb. 28 |
|
#76 |
Old Noisy Room 202 |
| |
|
|
|
| Mar. 4 |
2007 |
#76a |
Architect Explains Rm. 202 |
| Mar. 4 |
|
#77 |
Too Green, or Not Green Enough? |
| Mar. 10 |
|
#78 |
The Green Question |
| Mar. 12 |
|
#79 |
First Floor Transoms, Or Not |
| Mar. 12 |
|
#80 |
Back in Auditorium Heaven |
| Mar. 19 |
|
#81 |
Rare View of SE Studios |
| Mar. 19 |
|
#82 |
Plenum of Mysteries Up in Attic |
| Mar. 25 |
|
#83 |
Plenum of Mysteries Solved |
| Mar. 26 |
|
#84 |
Fishbowl Revisited |
| Mar. 26 |
|
#85 |
More Fishbowl |
| Mar. 26 |
|
#86 |
Auditorium Sans Scaffolding |
| |
|
|
|
| Apr. 9 |
2007 |
#87 |
Bathrooms Discovered on 2nd Floor |
| Apr. 10 |
|
#88 |
Progress in 2nd Floor Center |
| Apr. 10 |
|
#89 |
Brick Wall Covered Up |
| Apr. 12 |
|
#90 |
Whoops! Wall Too High |
| Apr. 12 |
|
#91 |
Nothing Wrong Here |
| Apr. 26 |
|
#92 |
New Staircase Views Open Up |
| Apr. 29 |
|
#93 |
Banister Ball Mystery, Part I |
| |
|
|
|
| May 1 |
2007 |
#93a |
Banister Ball Mystery, Part II |
| May 1 |
|
#94 |
Auditorium Seats |
| May 3 |
|
#95 |
Yellow Brick Re-Exposed |
| May 3 |
|
#96 |
Honest |
| May 4 |
|
#97 |
NW Studios |
| May 6 |
|
#98 |
Auditorium Update |
| May 7 |
|
#99 |
Sink, South Wing |
| May 8 |
|
#100 |
A New Openness |
| May 9 |
|
#101 |
Raw Skylight |
| May 10 |
|
#102 |
SE Studios in 1909 and 2007 |
| May 13 |
|
#103 |
Let There Be Light |
| May 13 |
|
#103a |
Horizontal Light |
| May 14 |
|
#104 |
Let There Be Heat, Too |
| May 23 |
|
#105 |
Frieze Installed |
| May 30 |
|
#106 |
The Friezer |
| |
|
|
|
| June 3 |
2007 |
#107 |
High Summer Light |
| June 4 |
|
#108 |
Nearing Finish |
| June 6 |
|
#109 |
The Frieze Way, Revisited |
| June 6 |
|
#110 |
Skylight in NE Studios |
| June 12 |
|
#111 |
A Rough Cut Finish |
| June 12 |
|
#112 |
More Rough Cut Finish |
| June 13 |
|
#113 |
A Ceiling Fan at Finish |
| June 13 |
|
#114 |
How 'bout Splat! For Finish? |
| June 22 |
|
#115 |
The Palace of Red Linoleum |
| June 22 |
|
#116 |
Historic Photo Revisited on Solstice |
| |
|
|
|
| July 21 |
2007 |
#117 |
Finished: The End is Here |
| |
|
|
|
| Aug. 20 |
|
#118 |
First Students in Architecture Hall |